The Erickson Avenue/Stone Spring Road Connection is a 3.1-mile long project corridor developed to address the needs for improved street system connectivity, provide better east to west mobility, and address deficient capacity and critical safety concerns in the southern portion of the City of Harrisonburg.
The project also accommodates alternative transportation users (bicyclists and pedestrians) with on-road bicycle lanes and sidewalks.
Phase I for corridor improvement is a 0.23-mile section of Erickson Avenue at the intersection of Route 42 that is currently under construction.

(click here for larger map)
Bids for Phase II construction accepted April 2010. Awarded to Perry Engineering Company, Inc.. Construction to begin July 2010.
Phase I began February 2009.
- Expect changes to traffic patterns at intersection of S High St (Rt 42) and Erickson Ave. More info.